New Pennsylvania Maps of US 219 and Status Updates**Courtesy of PennDOT
- 219 Alternatives Map (PDF document)
Alternate US 219 Study
Status: 4-lane limited access facility, which is not on the Appalachian Development Highway System and therefore not eligible for APD funds, was deferred in 2004 due to estimated cost of $500 million. A new alternate route for US 219 was then studied to help meet the needs of the area. The focus of this study was to identify lower cost, on-line improvements that could be made to act as a second north-south corridor in the northern Cambria County region. The study has been completed and the improvement recommendations will be presented publically this fall.
Funding Needs (All 9 Improvements):
o All phases - $34.5 million
- Meyersdale to Somerset (PDF document)
US 219 I-68 to Meyersdale 8 miles (6 miles in PA)
Status: Due to funding limitations, this project was put on hold in early 2008. Prior to the stop work, the project team was finalizing the Draft Environmental Impact Statement.
Funding Needs (PA Portion Only):
o Preliminary Engineering/EIS - Fully Funded
o Final Design - $11 million
o Utilities - $10 million
o Right of Way - $30 million
o Construction - $200 million
US 219 Garrett Meyersdale to Somerset 11 miles
Status: Current efforts are geared toward permit acquisition. The right of way appraisal process is currently underway with acquisition scheduled to begin this fall. The project is on schedule for construction to begin in 2011, pending funding availability.
Funding Needs (PA Portion Only):
o Preliminary Engineering/EIS - Fully Funded
o Final Design - Fully Funded
o Utilities - Fully Funded
o Right of Way - Fully Funded
o Construction - $305 million*
*$244 million of Federal APD funds (Wont be obligated until all funds are identified), $61 million of State matching funds (Need $35 million or approval to use toll credits)
- New Proposed 219 Map (PDF document)